Many Watertown Street Repair Projects Must Wait Until Spring
Most repair projects have started, but the final resurfacing will have to wait on most.
About a third the streets on the town’s repair list are finished, but others will have to wait until after the winter to be completed, Public Works Superintendent Gerald Mee told Town Councilors. The town had seven streets on the schedule to be resurfaced, and have other improvements and Mee said, who said the summer 2012 projects are about 50 percent complete. Work on two roads has been completed – Middlesex Road and Hawthorne Road, Mee said. Others will take longer, Mee said during the Public Works Subcommittee meeting. “We have completed water service replacement on Boyd (Street), Union (Street), Standish (Road) and Lovell (Road), and they are ready for road construction,” Mee said. The work will likely have to wait for warmer weather, …